[Translate to English:] Basic requirements before laying the flooring:
1. About the base: it is best if the base is asphalt or concrete. Installation over damaged or uneven base is not allowed
2. The room temperature should be between +15 и +25 ºС.
3. Installation of fences and lights should be finished.
Flooring installation includes the following actions:
1. Shipping of materials to the site
2. Base cleaning from dust and other contaminations.
3. Laying of the flooring.
- application of ground coat.
- installation of the acrylic flooring. It can be on more than one layer, depending on the thickness. If there is more than one layer, every layer should be left to dry for 24 hours. Depending on the meteorological condition more time may be needed.
4. Making of outlines. Depends on the ground type - tennis, basketball, multifunctional, etc.
The following actions are not included in installation::
1. Cleaning after installation..
2. Shipping and installation of various accessories.
3. Also fences, lights, base preparation, etc. can be done if the client wishes to